General
- Safety issues are an output from the Commission’s analysis. They may not always relate to factors directly contributing to the accident or incident. They typically describe a system problem that has the potential to adversely affect future transport safety.
- Safety issues may be addressed by safety actions taken by a participant, otherwise the Commission may issue a recommendation to address the issue.
Safety issue 1: The risk assessment for the commissioning of signal 308 was incomplete and did not identify all the hazards associated with the positioning of the signals. The opportunity to implement risk controls to address those hazards was missed, resulting in the correct signal not being observed and a wrong signal being responded to, increasing the risk to rail users.
-
Since this incident, KiwiRail has identified two options to mitigate the sighting risk associated with signal 308:
Option 1: Eliminate 312 Signal. This is KiwiRail’s preferred option but does require extensive re-signalling of the Onehunga Junction; or
Option 2: Relocate signal 308 to the left-hand side of the Up Main suspended from a gantry structure and introduce a Banner Indicator on approach.
- KiwiRail is continuing work to make a determination on the path forward for each option.
- With respect to improving the process of commissioning signals, KiwiRail acknowledge this as part of its continuous improvement programme. In the decade since the AEP project, a number of initiatives have been adopted to improve the signals’ sighting process, including:
-
The signals sighting standard S-ST-SG-2124 and associated task instruction S-TI-SG-2203, which were produced in 2017 to update and improve the requirements for signals sighting. This document outlines the requirements for new works and modifications, maintenance and post incident.
-
With the emergence of digital engineering, virtual tools that are being used to determine signals’ sighting in areas where significant change is occurring. There are several recent examples of this in both the Auckland and Wellington suburban areas. This technology enables an initial signals sighting assessment (and removal of sighting constraints) at design stage, well in advance of construction. Final confirmation is still undertaken with a Signal Sighting Committee before being brought into use.
- The Commission welcomes the safety action to date with respect to signal 308 and the signal commissioning process more generally. However, with respect to signal 308, as the mitigation measures have yet to be implemented, the Commission has made a recommendation in Section 6 to address this issue.
Safety issue 2: The use of different engineering risk controls on rail vehicles using the Auckland metro network results in varying levels of protection, increasing the complexity of the rail system.
- The commissioning of ETP on Te Huia passenger services is a step towards the introduction of an engineering control that mitigates the event of a signal passed at stop. The Commission understands that there are other train services operating on the Auckland commuter rail network that do not have any engineering controls and operated in capacities similar to Te Huia’s at the time of the Penrose incident.
- The Commission welcomes the safety action taken to date. However, it believes more actions need to be taken to ensure the safety of future operations. Therefore, the Commission has made a recommendation in Section 6 to address this issue.
Safety issue 3: KiwiRail’s locomotive engineer route knowledge training system was inadequate to identify gaps in knowledge or reduced frequency of exposure to a route. This means that locomotive engineers may have insufficient knowledge to drive on a particular route safely.
- Since the incident, KiwiRail has designed and delivered a route knowledge training package to all Te Huia LEs and those who drive freight. The training includes videos of the route from Westfield to The Strand (and return) along with Signal and Interlocking Diagrams with specific points to note (such as Speed Indicators and irregular signal positions). This training has also been observed in practice for each individual LE by the Occupation Competency Manager on week one of the Te Huia start up after this incident, month one, and month three, to ensure all staff are competent.
- The Commission welcomes the safety action to date. However, it believes more actions need to be taken to ensure the safety of operations for all LEs on all routes, not just Te Huia LEs. Therefore, the Commission has made a recommendation in Section 6 to address this issue.